Comprehensive Gantt Chart Example for Project Planning

School
University of Manitoba**We aren't endorsed by this school
Course
ENG 1430
Subject
Industrial Engineering
Date
Dec 10, 2024
Pages
6
Uploaded by ChancellorRhinoceros4741
Gantt Chart ExampleTask #Task ListPredecessorStart DatePhase 1Problem Definition1Appoint Project Manager12017-02-012017-02-012Form a Problem Statement12017-02-012017-02-01312017-02-012017-02-014Conduct stakeholder interviews12017-02-012017-02-015Review Target Specifications with new information412017-02-022017-02-026Establish meeting schedule for your Team and assign responsibilities12017-02-012017-02-01Phase 2Conceptual Design (Formulating Solutions)71, 2, 3, 4, 5, 642017-02-032017-02-068Evaluate alternatives against identified target specifications722017-02-072017-02-089Select a design (Decision-Making)812017-02-092017-02-09Phase 3Models and Prototypes10Collect materials needed to build the prototype932017-02-102017-02-1211Build the prototype1022017-02-132017-02-1412Test the prototype1112017-02-152017-02-1513Revise and refine the prototype1222017-02-162017-02-1714Finalize and present design1312017-02-182017-02-18Phase 4Design Implementation1412017-02-192017-02-19NotesAssume the team will work 7 days a weekDates are inclusiveDuration (in days)Finish dateIdentify Target SpecificationsIdentify alternatives for the Design Parameters(Brainstorm)
Background image
Gantt Chart ExampleProject Gantt ChartTask #Predecessorration [daFeb. 1/17Feb.2/17Feb. 3/17Feb. 4/17Feb. 5/17Feb. 6/17Feb. 7/17Feb. 8/17Feb. 9/17Feb. 10/17Feb. 11/17Feb. 12/17Feb. 13/17Feb. 14/17Feb. 15/17Feb. 16/17Feb. 17/17Feb. 18/17Feb. 19/17Feb. 20/17Feb. 21/17Phase 11121314154161Phase 271, 2, 3, 4, 5, 64872981Phase 3109311102121111312214131Phase 4141NotesAssumed the team will work 7 days a week
Background image
Gantt Chart ExampleProject Gantt ChartPhase 11121314154161Phase 271, 2, 3, 4, 5, 64872981Phase 3109311102121111312214131Phase 4141NotesAssumed the team will work 7 days a weekTask #PredecessorDuration [daysFeb. 1/17Feb.2/17Feb. 3/17Feb. 4/17Feb. 5/17Feb. 6/17Feb. 7/17Feb. 8/17Feb. 9/17Feb. 10/17Feb. 11/17Feb. 12/17Feb. 13/17Feb. 14/17Feb. 15/17Feb. 16/17Feb. 17/17Feb. 18/17Feb. 19/17Feb. 20/17Feb
Background image
Gantt Chart ExampleProject Gantt ChartPhase 11121314154161Phase 271, 2, 3, 4, 5, 64872981Phase 3109311102121111312214131Phase 4141NotesAssumed the team will work 7 days a weekTask #PredecessorDuration [daysFeb. 1/17Feb.2/17Feb. 3/17Feb. 4/17Feb. 5/17Feb. 6/17Feb. 7/17Feb. 8/17Feb. 9/17Feb. 10/17Feb. 11/17Feb. 12/17Feb.13/17Feb. 14/17Feb. 15/17Feb. 16/17Feb. 17/17Feb. 18/17Feb. 19/17Feb. 20/17Feb
Background image
Gantt Chart ExampleProject Gantt ChartPhase 11121314154161Phase 271, 2, 3, 4, 5, 64872981Phase 3109311102121111312214131Phase 4141NotesAssumed the team will work 7 days a weekTask #PredecessorDuration [daysFeb. 1/17Feb.2/17Feb. 3/17Feb. 4/17Feb. 5/17Feb. 6/17Feb. 7/17Feb. 8/17Feb. 9/17Feb. 10/17Feb. 11/17Feb. 12/17Feb.13/17Feb. 14/17Feb. 15/17Feb. 16/17Feb. 17/17Feb. 18/17Feb. 19/17Feb. 20/17Feb
Background image
Gantt Chart ExampleProject Gantt ChartPhase 11121314154161Phase 271, 2, 3, 4, 5, 64872981Phase 3109311102121111312214131Phase 4141NotesAssumed the team will work 7 days a weekTask #PredecessorDuration [daysFeb. 1/17Feb.2/17Feb. 3/17Feb. 4/17Feb. 5/17Feb. 6/17Feb. 7/17Feb. 8/17Feb. 9/17Feb. 10/17Feb. 11/17Feb. 12/17Feb. 13/17Feb. 14/17Feb. 15/17Feb. 16/17Feb. 17/17Feb. 18/17Feb. 19/17Feb. 20/17Feb