PROJECT MANAGEMENT PLAN
10/16/2016
Mooney’s Bay Play Structure
Team AG 6:
Can Cambazoglu Fangzheng Zhang
Shreyan Noronha Sinthia Ingrid Chris Duncan Joshua Snider
Supervisor:
Angela Clermont
Content:
Project Charter
1. Project Description 3
2. Objective 3
3. Scope Statement 3
4. Key Assumptions 3
5. Constraints 4
6. Risks 4
7. Stakeholders 4
8. Project Milestones 4
9. Project Roles and Responsibilities 5
10. Authorization…………………………………………….……………………………………………………………………….…………5 Other Inputs
…show more content…
Scope Statement
The project scope will include: ϖ Designing and constructing a play structure for children
♣ Community approvals
♣ Construction permits
♣ Meet safety and accessibility standards
Deliverables:
ϖ The high level/key deliverable for the project includes:
♣ A one acre play ground in the shape of the map of Canada consisting of 10 individual structures
♣ Minimize the environmental impacts of the construction on the surrounding area
Out of Scope:
♣ No modifications to the existing structures within Mooney’s Bay Park
4. Key Assumptions ϖ Project will be completed on time and within the budget ϖ Prevention of possible issues that might disrupt the community or the natural habitat of the area ϖ Rules and regulations regarding the construction will be taken into account ϖ Meteorological events will not hinder the process 5. Constraints ϖ The project must be completed before July 1st ϖ City of Ottawa’s portion of the budget is 959,750 CAD ϖ Sinking Bay Ship will be the only partner other than the City of Ottawa.
6. Risks ϖ Community protests could delay the project ϖ Protect the safety of workers ϖ Changing regulations regarding our project
7. Stakeholders ϖ Sinking Ship Entertainment Inc. ϖ City of